Monday, 15 July 2013

Week 12 and What's to come......

Summary of this week as been completion of the rendering outside - still need the bottom level to be painted though, all gyprock hung and the actual plastering completed.  Once again with a visit to the house on Saturday, we found all the plasterers in action.

Best part is - scaffolding has been removed and the unveiling of the house without it!






















Next steps.....

This coming week
 - the 'Fixing' of everything - cornice, architrave, doors hung
 - Carpenter to return and get stuck into garage roof and alfresco roof now scaffolding down
 - bi-fold door installed - "finalise lock up" - also means I will definitely be LOCKED OUT!

Following week 
 - Fit out - staircase and cabinetry (kitchen/bathrooms/laundry)
 - Roofing onto Garage and Alfresco

Week after
 - Painter begin

Week or 2 after that
 - Tilers


Plastering photos:

Looking from Kitchen across dining to back bi-folds

Looking straight to Front Door

Family Room

Laundry - Linen to the left, will be full length
bench down right

Main Bathroom - Shower Nook
Master Bedroom



Master Ensuite

Master WIR - LOVE it!



















Games Room and Study Nook

Study Nook outside Master Suite (left) and Stairwell (right)
Games Room (Upstairs)




The Rubbish Pile!
I can not believe the mess of food waste/packaging that the tradies just throw onto the ground all around the house and in the house.  