Saturday, 16 November 2013

What we Love and What we would do differently....

Things I would do differently on the Wembley 35 - 

  • Bed 3 - I would have changed window location to be facing backyard, this would have assisted with a larger window and saved overlooking issue.
  • Guest Bedroom - pay close attention to where the BIR is placed. Due to us choosing the Balmain facade, it is in a strange location just inside the door, but right in front of a feature window. It would fit perfectly on the far outside wall, however you are then looking straight into the cupboard and then a bed would have to be on the wall just inside the door (on the hall wall)
  • Laundry Chute - Love having it, it is super, however they have struggled with it the whole time and still need to fix it up.  The actual hole for clothes is 250mm x 250mm!!!!!  I was trusting that they knew what they were doing, however no-one knew what to do.  Big balls up.  Still ongoing.
  • Bifold Door to Alfresco - we have a 4 leaf aluminium door and it doesn't have a single opening door. Very strange design. Wish I had realised this in the planning stage as this we should have read on the plans. Also put in retractable flyscreens if you can or at least get a quote. We didn't but I found out later on that others have got them installed.
  • Pay close attention to the size of the cupboards in the kitchen, especially if you like them all uniform. One of ours on the plans was 350mm and all the rest 400mm, ridiculous that they do it that way!
  • Laundry Bench is 3800mm long.  Found out laminate/formica is only in 3600mm lengths, so therefore ugly join on the bench top.

Things we LOVE:
  • Green Splashback - Dulux Mangrove Leaf - very fresh, everyone comments on it.
  • The extra "media unit" that extends from the kitchen along the dining wall under the window. Everyone that walks into our house comments on it and how wonderful it is. We put draws instead of cupboards. Great utilisation of space and worth the money.
  • Laundry size - with changing the lounge to a guest bedroom, the reorganisation of design makes a wonderful massive laundry - LOVE IT.
  • Grand Alfresco - fantastic if you can afford to do it.
  • Happy with our selection of lighting. We have 5 wall lights round stairs, probably only needed 3.
  • We went for the Amended Pantry Option for kitchen same as the display.
  • Size of the Pantry
  • Size of Parent's WIR
  • Tiling - Tiler did a fantastic job.  Very Shmick.  The Cat 1 Subway tiling is great, I have had lots of comments on them - they are in laundry splashback, round bathtub and quest ensuite shower.
  • Casement Windows
  • Double glazed windows
  • Hebel - very stable temperature so far
  • Bolero Flooring - this has been fabulous with 3 young children and a house surrounded by dirt!








Monday, 15 July 2013

Week 12 and What's to come......

Summary of this week as been completion of the rendering outside - still need the bottom level to be painted though, all gyprock hung and the actual plastering completed.  Once again with a visit to the house on Saturday, we found all the plasterers in action.

Best part is - scaffolding has been removed and the unveiling of the house without it!






















Next steps.....

This coming week
 - the 'Fixing' of everything - cornice, architrave, doors hung
 - Carpenter to return and get stuck into garage roof and alfresco roof now scaffolding down
 - bi-fold door installed - "finalise lock up" - also means I will definitely be LOCKED OUT!

Following week 
 - Fit out - staircase and cabinetry (kitchen/bathrooms/laundry)
 - Roofing onto Garage and Alfresco

Week after
 - Painter begin

Week or 2 after that
 - Tilers


Plastering photos:

Looking from Kitchen across dining to back bi-folds

Looking straight to Front Door

Family Room

Laundry - Linen to the left, will be full length
bench down right

Main Bathroom - Shower Nook
Master Bedroom



Master Ensuite

Master WIR - LOVE it!



















Games Room and Study Nook

Study Nook outside Master Suite (left) and Stairwell (right)
Games Room (Upstairs)




The Rubbish Pile!
I can not believe the mess of food waste/packaging that the tradies just throw onto the ground all around the house and in the house.  




Saturday, 6 July 2013

Half Way There.......Week 11 !!!

Well I can't believe it and must say, a tad excited!  I met the SS a week ago on site to discuss a couple of things.  I asked how long did he think until we would be finished???
Remembering - Our Contract states a build time of 280 days + 28 days for Christmas period = 44 weeks.
At the time of my discussion with SS we are up to Week 10.  He replies that we are pretty much half way there, so probably around 10 weeks to go.  Me gobsmacked!
I knew that they were well advanced, hubby and I couldn't work out how on earth it could take till Jan/Feb 2014 with where we are up to.
So, that 10 weeks takes us to early September (which would equate to around 22 week build time).  I don't mind if it is even October, this is well before Christmas with time to get settled in.  Not holding my breath just yet though.

Must get onto some other quotes now such as fences, driveways and pool fencing!

Lock-Up Independent Inspection
Nothing to report other than the obvious things missing - windows, bi-folds, alfresco roof and garage roof.  So a good job being done.



So where are we up to.........

Eaves
The Eaves have now been painted.














Missing Window and Rendering
The missing window has been installed and thus the Hebel that goes around it.  This area now needs to be rendered.  I am sure that this will happen early this coming week as the SS wants the scaffolding down asap (actually last week!)

I noticed that there is a chip in the render around one of the top storey facade windows.  I will have to make sure I find the Renderers on site this week and ask them to fix it if they haven't noticed.  Stands out though!  You can see it in this picture here.










Back Bi-Fold
Still missing.  Was told that this would be installed this last week, but not there.  It really needs to be on before they plaster!

Insulation
All the Insulation has been installed.  Glad I was there though.  Happened to ask "What does the sound insulation look like?".  Dumb look from installer stating that there wasn't any sound insulation on this order.  I confirmed that there should be.  Anyway, after them chasing it up, it was missed off the order and is now installed around our Media/Playroom.

Extra Insulation in roof.
Sound Insulation is Grey


Electricals
Electricians did come back and move junction boxes that we had at the back of the house and insert a separate circuit that we added as a PCV.  These junction boxes are for the pool electricals.  One of the junction boxes was going to end up way up high at lighting height, however I asked for it to be put down low as otherwise we would have to cover wiring all the way up the wall.  One of the junction boxes is linked up to an internal light switch to turn on the pool lights.  The other junction box will hook up wiring to the pool equipment after handover.

Plaster
All the plaster and cornices have now been delivered and this is the next step internally.  Am guessing that the staircase can't be far away either...